Main Cable Installation Completed at 1915Çanakkale Bridge
The last of the 288 steel cables has been spun between the towers of the 1915Çanakkale Bridge, and thus the main cable operations has been completed.
The last of the 288 steel cables has been spun between the towers of the 1915Çanakkale Bridge, and thus the main cable operations has been completed.
The giant floating crane “Asian Hercules III”, which will be used for deck installation, has arrived to 1915Çanakkale construction site.
The first of the 87 deck blocks which will constitute the roadway of 1915Çanakkale Bridge has been placed on the Asian tower’s working platform by the giant floating crane “Asian Hercules III”.
Installation of the hanger ropes onto the main cable has started at 1915Çanakkale Bridge. Later on, the deck blocks will be attached to the hanger ropes.
The installation of the deck blocks, which will constitute the roadway of 1915Çanakkale Bridge, has started.